Project: Central Glasgow

Works: Installation of chemical grout tubes to stabilise an existing building.

Equipment used: Atlas “Bunny” rig with Morath rotary percussive drill head

Project Details

A very small, light drilling unit with a remote hydraulic power pack was lifted into the large hole in the centre of Glasgow.

75mm diameter temporary casings, in 1.0mtr lengths, were driven into the sandy sub soil to a depth of 10mtrs. Grout injection tubes were then lowered inside the casings, ready for chemical grouting to take place once the casings had been removed.